Progressing the plan
With the groundwater
licence process now concluded, we are progressing development of
the final Mine Rehabilitation and Closure Plan (MRCP) based on a
natural filling approach for the former mine pit.
The final MRCP will set
out the work required to achieve a safe, stable and sustainable
landform and support the eventual return of the site to the
community.
Recent work includes:
- Working with the mine
regulator, Resources Victoria, to confirm the requirements and
expectations for the final MRCP.
- Reconfirming the
expected timeframe for the mine pit to fill naturally, with current
modelling indicating it will be approximately 50 years.
- Reconfirming
geotechnical, erosion and vegetation management strategies aligned
with the natural filling process.
- Developing a long-term
water quality forecast model for the mine water body. Long-term
water quality is expected to be consistent with naturally occurring
background water quality in the local catchment.
- Planning community and stakeholder engagement
activities ahead of submitting the final MRCP.
Subject to consultation
and regulatory requirements, we expect to submit the final MRCP to
Resources Victoria in the first half of 2027.
|
|
|
|
|
|
Sharing knowledge and
perspectives
Engagement with key
stakeholders continues to play an important role in rehabilitation
planning and implementation.
Recently we have
engaged with community groups, Traditional Owners, regulators and
rehabilitation specialists to share information, receive feedback
and ensure rehabilitation and future planning are informed by a
range of perspectives and expertise.
Site visitors included
Friends of Anglesea River, Corangamite Catchment Management
Authority, the Queensland Mine Rehabilitation Commissioner,
environmental science students from Damascus College and a
24-member Resources Victoria Compliance Officer team.
The visits provided
opportunities to discuss rehabilitation progress, mine water
filling, environmental management, long-term planning and lessons
from other rehabilitation projects.
Alcoa team members also
participated in the annual Angair Wildflower and Arts Show. The
spring event attracted people from all over the region and provided
another valuable opportunity to hear community perspectives and
answer questions about rehabilitation activities and the site’s
future.
|
|
|
|
|
|
|
|
|
Rehabilitation and environmental
management
Rehabilitation,
environmental monitoring and mine maintenance activities continue
across both the former mine and power station areas.
A key focus has been
the continued implementation of our long-term lower-slope erosion
mitigation strategy. Slope preparation, irrigation system
installation and lime application were completed ahead of the final
kikuyu establishment program on the northern and eastern slopes of
the former mine. This builds on work undertaken over the past two
years and represents the final phase of the lower-slope
revegetation program.
Other activities
include:
- Continued vegetation
and weed management works, including treatment of woody weeds such
as Sallow Wattle and Boneseed, small known occurrences of Serrated
Tussock, and other invasive species such as African Weed Orchid,
Watsonia, Pampas Grass and Thistle. These works covered an area of
more than 90 hectares.
- Ongoing weed monitoring and soil and nutrient testing
across the mine’s native Wallaby Grassland areas, covering an area
of approximately 50 hectares.
|
|
|
|
|
|
Power station progress
Preparations continue
to complete the final step in the Environment Protection Authority
(EPA) environmental audit process for the former power station
site.
This includes
developing a Site Condition Report ahead of the future
EPA-appointed auditor’s final Site Audit Statement, which will
confirm satisfactory completion of all remediation activities and
the site’s suitability for potential future land uses.
The Alcoa Water Storage
Pond lease was recently extended until 31 March 2027 to
support the Department of Energy, Environment and Climate Action’s
continued management of the lower Anglesea River. This has however
delayed the final site environmental audit process by nine months,
with completion now anticipated in late 2027.
|
|
|
|
Future land use planning
We continue to
investigate future land use opportunities for our freehold land,
consistent with the Alcoa Concept Freehold
Master Plan and the Anglesea Futures Land Use
Framework.
This includes ongoing
engagement with government agencies, local authorities and other
stakeholders about potential future uses for parts of the site.
Alcoa and the Surf
Coast Shire have also had positive discussions to resolve the
long-term future of the Anglesea Bike Park, which is currently
located on Alcoa freehold land.
|
|
|
|
Want to know more?
To read more about our
activities, including previous community updates, visit the
Anglesea section of the Alcoa Australia website www.alcoa.com/australia/en/anglesea.
|
|
|
|
|
|
|
|
|
|
|
|