Progressing the plan  

 

With the groundwater licence process now concluded, we are progressing development of the final Mine Rehabilitation and Closure Plan (MRCP) based on a natural filling approach for the former mine pit.

 

The final MRCP will set out the work required to achieve a safe, stable and sustainable landform and support the eventual return of the site to the community.

 

Recent work includes:

  • Working with the mine regulator, Resources Victoria, to confirm the requirements and expectations for the final MRCP.
  • Reconfirming the expected timeframe for the mine pit to fill naturally, with current modelling indicating it will be approximately 50 years.
  • Reconfirming geotechnical, erosion and vegetation management strategies aligned with the natural filling process.
  • Developing a long-term water quality forecast model for the mine water body. Long-term water quality is expected to be consistent with naturally occurring background water quality in the local catchment.
  • Planning community and stakeholder engagement activities ahead of submitting the final MRCP.

Subject to consultation and regulatory requirements, we expect to submit the final MRCP to Resources Victoria in the first half of 2027.

 

Sharing knowledge and perspectives 

 

Engagement with key stakeholders continues to play an important role in rehabilitation planning and implementation.

 

Recently we have engaged with community groups, Traditional Owners, regulators and rehabilitation specialists to share information, receive feedback and ensure rehabilitation and future planning are informed by a range of perspectives and expertise.

 

Site visitors included Friends of Anglesea River, Corangamite Catchment Management Authority, the Queensland Mine Rehabilitation Commissioner, environmental science students from Damascus College and a 24-member Resources Victoria Compliance Officer team.

 

The visits provided opportunities to discuss rehabilitation progress, mine water filling, environmental management, long-term planning and lessons from other rehabilitation projects.

 

Alcoa team members also participated in the annual Angair Wildflower and Arts Show. The spring event attracted people from all over the region and provided another valuable opportunity to hear community perspectives and answer questions about rehabilitation activities and the site’s future. 

 

Rehabilitation and environmental management 

 

Rehabilitation, environmental monitoring and mine maintenance activities continue across both the former mine and power station areas.

 

A key focus has been the continued implementation of our long-term lower-slope erosion mitigation strategy. Slope preparation, irrigation system installation and lime application were completed ahead of the final kikuyu establishment program on the northern and eastern slopes of the former mine. This builds on work undertaken over the past two years and represents the final phase of the lower-slope revegetation program.

 

Other activities include:

  • Continued vegetation and weed management works, including treatment of woody weeds such as Sallow Wattle and Boneseed, small known occurrences of Serrated Tussock, and other invasive species such as African Weed Orchid, Watsonia, Pampas Grass and Thistle. These works covered an area of more than 90 hectares.
  • Ongoing weed monitoring and soil and nutrient testing across the mine’s native Wallaby Grassland areas, covering an area of approximately 50 hectares.

 

Power station progress 

 

Preparations continue to complete the final step in the Environment Protection Authority (EPA) environmental audit process for the former power station site.

 

This includes developing a Site Condition Report ahead of the future EPA-appointed auditor’s final Site Audit Statement, which will confirm satisfactory completion of all remediation activities and the site’s suitability for potential future land uses.

 

The Alcoa Water Storage Pond lease was recently extended until 31 March 2027 to support the Department of Energy, Environment and Climate Action’s continued management of the lower Anglesea River. This has however delayed the final site environmental audit process by nine months, with completion now anticipated in late 2027.

 

Future land use planning

 

We continue to investigate future land use opportunities for our freehold land, consistent with the Alcoa Concept Freehold Master Plan and the Anglesea Futures Land Use Framework.

 

This includes ongoing engagement with government agencies, local authorities and other stakeholders about potential future uses for parts of the site.

 

Alcoa and the Surf Coast Shire have also had positive discussions to resolve the long-term future of the Anglesea Bike Park, which is currently located on Alcoa freehold land.

 

Want to know more?

 

To read more about our activities, including previous community updates, visit the Anglesea section of the Alcoa Australia website www.alcoa.com/australia/en/anglesea.

 